Arterial Road Rehabilitation

Project Purpose and Overview

The purpose of this project is to rehabilitate or repave portions of Waterman Road and Elk Grove Florin Road while also adding class II (on-street) bike lanes. The City will design and construct a mid-block pedestrian crossing with a rectangular rapid flashing beacon along Elk Grove-Florin Road north of Valley Oak Lane. The project also includes upgrading curb ramps to Americans with Disabilities Act (ADA) standards. Future connectivity will be made possible along Waterman Road for the City's bike lane network, while reducing annual pavement maintenance costs, extending the life of the road pavement, and improving ride quality.


Current Status

On May 25, 2022, the City Council adopted a resolution authorizing the City Manager to execute a construction contract with George Reed, Inc.  On June 9, 2022, the City executed the construction contract with George Reed, Inc.  It is anticipated that the Contractor will be working from July 2022 through January 2023.   

During construction, the Contractor will provide funding identification signs and necessary traffic controls to ensure traffic impacts are minimized.  The Contractor will also provide information on traffic delays and alternate routes, necessary driveway closures, temporary relocation of bus stops, adjustment of utilities, and waste pick up. 

There will be a full closure of sections of Waterman Road during the progress of the work.  These will be phased to minimize impacts to the motoring public.  Appropriate signs, detours, and advance notifications will be provided by the Contractor. 


Exhibits

View Map

View Map Larger


Funding

Source Amount
SB1 Streets and Roads $1,340,000
Measure A Maintenance $1,919,903
Federal Grant #1 $2,700,000
Elk Grove Roadway Fee $275,000
External Agencies - $23,400 
Federal Grant #2 $845,697
Drainage Fee $1,040,000
Total $8,144,000

Public Outreach


Environmental Document

City Council adopted the CEQA Initial Study and Mitigated Negative Declaration on September 23, 2020. Caltrans issued the NEPA Categorical Exclusion on January 20, 2021.


Project Schedule

Date Description
October 2018 Project was presented to Trails Committee and Open House conducted
April 2021 Complete Final Design
November 2021-June 2022 Utility Relocations
April 2022 Advertise Project for Construction
May 2022 Award Construction Contract
Summer 2022 - Winter 2023 Construct Improvements