Project Purpose and Overview
The purpose of this Project is to provide necessary improvements to Railroad Street and adjacent sidewalks in support of the City's goal to develop a multi-use outdoor plaza and pertinent infrastructure in the city's historic district. The Project is needed for improved flow of traffic for travelers, as well as improved accessible ramps and sidewalks for safety and efficiency.
The City of Elk Grove (City) in coordination with the Department of Housing and Urban Development (HUD) plans to construct roadway improvements on Railroad Street. The proposed improvements consist of road reconstruction, utility construction (wet and dry/joint trench), construction of new curbs, gutters, accessible sidewalks and ramps, Street Lights and construction of two parking lots (with lighting, landscape and irrigation improvements) along an approximate 2,000-foot long segment of Railroad Street and approximately 180 foot segment of Grove Street. Sidewalks are proposed along the east and west sides of Railroad Street and along the north and south sides of Grove Street. Ramp reconstruction is proposed at the intersection of Elk Grove Boulevard and Railroad Street and several new accessible ramps will also be constructed. New gas, sanitary sewer, storm drain, and water lines are proposed along Railroad Street and Grove Street.
Permanent right-of-way acquisitions and tree agreements have been completed along Railroad Street and Grove Street to accommodate the Project. Temporary construction easements, utility easements, and encroachment permits may be needed on a limited basis to accommodate the installation of the proposed improvements. Existing private utilities will remain active during project construction. No road closures are anticipated to occur and access to each residence and business will be maintained. Minor temporary detours for local traffic may take place and construction is anticipated to last eleven months.
Exhibit
View larger
Environmental
Review the Environmental documents here:
Funding
The project is funded by Community Development Block Grant (CDBG), Measure A, Senate Bill 1 Local Street and Roads (SB 1 LSR), Drainage Fee, and General Fund Capital Reserve.
Current Status
The construction contract for the Railroad Street Improvements (WTR049) and the Old Town Plaza Phase 2 and 3 (WCE022) Projects was awarded to Western Engineering Contractors, Inc. by Council at their May 13, 2020 meeting. Construction began on June 8, 2020 and is anticipated to be completed in the Spring of 2021.
Schedule
Date |
Description |
July 25, 2018 |
Design and Environmental Began |
March 26, 2019 |
Project was presented to the Disability Advisory Committee for feedback |
April 24, 2019 |
Environmental Document (Supplemental IS/MND) circulated for public review and comment |
May 14, 2019 |
Joint Open House meeting held to present Project to the community
|
June 21, 2019 |
Environmental Document (Supplemental IS/MND) public comment period ends |
July 24, 2019 |
City Council Approved Environmental Document |
December 2019 |
Design Completed |
January 15, 2020 |
Advertise to receive bids |
February 27, 2020 |
Bids Due Date |
March 11, 2020 |
Staff Report |
March 18, 2020 |
Re-advertise to receive bids |
April 9, 2020 |
Bid Due Date |
May 13, 2020 |
CC Staff Report |
June 8, 2020 |
Begin Construction |
Spring 2021 |
Construction Substantially Complete |
Spring 2022 |
Plant Establishment Period Complete |
Contact Information
Public Works |
Senior Civil Engineer
Kristin Parsons
|
Email or (916) 478-2236
8401 Laguna Palms Way
Elk Grove, CA 95758
|