Infrastructure repair work will generate road and lane closures at two locations in the City beginning on Monday, December 2, weather permitting.
Utility Pole Replacements
The Sacramento Municipal Utility District (SMUD) is scheduled to replace utility poles at the intersection of Elk Grove Boulevard and Franklin Boulevard December 2-4. This work will occur at night and generate lane closures on Elk Grove Boulevard between Franklin Boulevard and Four Winds Drive.
Affected Area: Elk Grove Boulevard from Franklin Boulevard to Four Winds Drive
December 2-4 – Two lanes closed in each direction from 7 p.m. to 6 a.m.
For questions or more information about this project, please contact the Public Works Department at (916) 478-2256.
Pavement Replacement on Poppy Ridge Road
Both directions of Poppy Ridge Road will be closed between Big Horn Blvd. and Knotts Drive beginning on Monday, December 2 until Monday, December 16. Crews will reconstruct a portion of the roadway as part of the Madeira South housing development. Residential and emergency access will be maintained during this closure.
Affected Area: Poppy Ridge Road from Big Horn Blvd. to Knotts Drive

For questions or more information about this project, please contact the Development Services Department at (916) 627-3436.
# # #