Project Purpose and Overview
The purpose of this project is to rehabilitate or repave portions of Waterman Road and Elk Grove Florin Road while also adding class II (on-street) bike lanes. The City will design and construct a mid-block pedestrian crossing along Elk Grove-Florin Road north of Valley Oak Lane. Future connectivity will be made possible along Waterman Road for the City’s bike lane network, while reducing annual pavement maintenance costs and extending the life of the road pavement for improve ride quality. Segment 9 on Elk Grove Boulevard is delayed due to right-of-way complexities and will be constructed at a later time.
Current Status
Environmental process was completed in January 2021 with the issuance of the NEPA Categorical Exemption. Current critical tasks are to finalize the Plans, Specifications and Estimate, and to coordinate relocation of the existing utilities with the utility providers.
Exhibits
View Map Larger
Funding
Source |
Amount |
SB1 Streets and Roads |
$790,000 |
Measure A Maintenance |
$2,296,833 |
Federal Grant #1 |
$2,000,000 |
Elk Grove Roadway Fee |
$275,000 |
Federal Grant #2 |
$845,697 |
Drainage Fee |
$1,040,000 |
Total |
$7,247,530 |
Public Outreach
Environmental Document
City Council adopted the CEQA Initial Study and Mitigated Negative Declaration on September 23, 2020. Caltrans issued the NEPA Categorical Exclusion on January 20, 2021.
Project Schedule
Date |
Description |
October 2018 |
Project was presented to Trails Committee and Open House conducted
|
April 2021 |
Complete Final Design
|
July-September 2021 |
Utility Relocations |
January 2022 |
Advertise Project for Construction
|
March 2022
|
Award Construction Contract
|
Summer - Fall 2022
|
Construct Improvements
|